====One Planet P0>P2 - Commander Center Upgrades V====
====One Planet P0>P2 - Commander Center Upgrades V====
We will assume that, after setting up the above 5 times, that by the time someone has trained Commander Center Upgrades V that they have a solid understanding of how the process works.
We will assume that, after setting up the above 5 times, that by the time someone has trained Commander Center Upgrades V that they have a solid understanding of how the process works.
Command Center Upgrades V allows us to add 2 additional Basic Industry Facilities and 1 addition Advanced Industrial Facility. This will increase the productivity of the Planet by 33%. To achieve maximum efficiency, the Extractor Control Units will need to be running at 18,000 Units per Hour to keep up with the increased demand. You will likely need to drop to 3 Extractor Heads on one resource to have enough space to fit the Advanced Industrial Facility. With some re-positioning of the Extractor Control Units closer to the main site, you can free up some fitting space by reducing the lengths of the links between the Extractor Control Units and the Storage Facility, which should allow you to place that fourths Extractor Head back out. It takes a little effort to get the positing right and can be fiddly, but at an increase of 33% is definitely is worth it to get it right.  
Command Center Upgrades V allows us to add 2 additional Basic Industry Facilities and 1 addition Advanced Industrial Facility. This will increase the productivity of the Planet by 33%. To achieve maximum efficiency, the {{co|coral|Extractor Control Units will need to be running at 18,000 Units per Hour}} to keep up with the increased demand. You will likely need to drop to 3 Extractor Heads on one resource to have enough space to fit the Advanced Industrial Facility. With some re-positioning of the Extractor Control Units closer to the main site, you can free up some fitting space by reducing the lengths of the links between the Extractor Control Units and the Storage Facility, which should allow you to place that fourths Extractor Head back out. It takes a little effort to get the positing right and can be fiddly, but at an increase of 33% is definitely is worth it to get it right.  
*Place the two addition Basic Industrial Facility first, then the Advanced Industrial Facility so that the P0 resources do not run into the transit limit between structures.
*Place the two addition Basic Industrial Facility first, then the Advanced Industrial Facility so that the P0 resources do not run into the transit limit between structures.
[[image:Nsc pi 15.png]]